1, Force Majeure

Force majeure clause


Force majeure clause = force majeure + + action


In the middle, we may encounter some inhuman factors or destruction. At this time, we need to negotiate in advance how to avoid unnecessary disputes.


Example 1: if encountering uncontrollable time or circumstances, it shall be regarded as force majeure, but not limited to fire, wind, flood, earthquake, explosion, rebellion, infection, quarantine and isolation.

If the force majeure fails to fulfill the obligations under the contract, the other party shall extend the time for the execution of the contract, and the extension shall be equal to the time of force majeure event.


Any event or circumstance beyond control shall be regarded as Force, regarded, ",", ",", ",", ",", ",", ",", ",", ",", ",", ",", ",".


Example 2: if the force majeure lasts for more than 6 months,

contract

The two sides should adjust the performance of the contract through friendly negotiation as soon as possible.

If no agreement can be reached between the two parties, arbitration shall be made according to the twelfth clause of the contract.


If the Force Majeure last over 6 months, the two parties of, two, Force, Majeure, last, and last,


2, Late Delivery and Penalty delayed delivery and

Penalty clause


In a contract, if a party fails to fulfill the contract fully or in accordance with the contract stipulations, it should be punished.


Example 1: if Party B fails to finish the project on time due to its own reasons, Party B shall pay a penalty for breach of contract, which is calculated at 1/1000 of the total price per day, that is, one thousand two hundred and sixty dollars.

  • Related reading

Us Product Barriers Escalate &Nbsp; Domestic Exporters Are Under Pressure.

Law lecture hall
|
2010/9/23 15:01:00
51

Identification Of Polycyclic Aromatic Hydrocarbons In Textiles And Leather

Law lecture hall
|
2010/9/21 15:18:00
70

Anti Dumping In Common Sense Of Foreign Trade

Law lecture hall
|
2010/9/18 17:59:00
85

The Actual Infringement Behind The Virtual Network

Law lecture hall
|
2010/9/17 18:37:00
51

Problems To Be Considered In Formulating Exhibition Industry Policy

Law lecture hall
|
2010/9/13 15:43:00
70
Read the next article

3 Secrets Of Women's Success In Business

How can female professional managers build up their personal brands and win the careers of men in the workplace in an increasingly gender breaking workplace? Where do they get the strength to compete with men? How can they become a big winner on the PK platform?